Zelan Bhd has secured a RM938 million contract for a substantial portion of the onshore and offshore civil works for Saudi Arabia's water and power plant project in Shuqaiq.

It said on Feb 2 that phase two of the Shuqaiq project was awarded to Zelan Arabia Co Ltd and Mitsubishi Heavy Industries. The contract involved engineering, procurement and construction of the plant.

Under the contract, Zelan would undertake offshore works to design and build the intake box culverts, discharge channel and fuel oil supply facilities. It has 42 months to complete the project after the notice for the work to proceed is given in March.

This is Zelan's second infrastructure project in Saudi Arabia. In July last year it secured a RM90 million civil works project for the Shuibah 3 independent water and power plant project.